Work remains on schedule at the Newcastle Refinery. As with everything we do, safety will dictate the recovery efforts and timeline. Our workforce is motivated and committed to the goal of a safely executed project and restart of the refinery.
Two specific projects make up most of our focus. Two large heaters were damaged in the incident on Feb 12. One of these is being repaired onsite, while the second will be replaced with a new heater currently being fabricated in Oklahoma. These parallel efforts are expected to allow partial restart of the refinery in mid-April. This partial start will allow the facility to run at a reduced rate and begin to produce needed transportation fuels such as gasoline, diesel, and jet fuel. We expect full production to be achievable in late May once the new heater arrives and is installed.
Wyoming Refining Company is committed to fulfilling the supply needs of our customers and the Back Hills region throughout the process and beyond.